The 2026 Annual Gravel Road Resheet Program commenced this week, as part of our investment in improving the condition, safety and durability of our gravel road network.
This year’s program is supported by an almost $900,000 budget and will see approximately 15 km of gravel roads re-sheeted across the Shire.
Preparation works have already been completed, including:
- re-establishing roadside drainage
- cleaning culverts
- undertaking tree works to ensure safe clearance
- preparing roads ahead of re-sheeting.
The program is expected to run through until the end of the year, weather permitting.
Investing in better gravel roads
This year, Council will be introducing an improved gravel material which has been trialled on several roads across the Shire, including Gardiner Street and Whitehills Road in Creswick, with excellent results. Roads where the material was trialled more than 12 months ago have also continued to perform well. While the new material comes at a higher initial cost, it is expected to provide a more durable road surface, reduce ongoing maintenance requirements and deliver a better driving experience for road users and improve whole-of-life costs.
This change reflects Council’s focus on achieving better long-term value from our road maintenance investment.
Road locations for resheeting
- Holcombe Road, Glenlyon
- McMahons Road, Glenlyon
- Cantillions Road, Musk
- Lakeside Drive, Hepburn
- Brandy Hot Road, Eganstown
- Lord Clyde Road, Clunes
- Albert Street, Clunes
- Foleys Road, Clunes
- Graham Road, Broomfield
- Elizabeth Street, Smeaton
- Looby Lane, Newlyn
- Campion Road, Newlyn
- Myles Road, Newlyn
- Shea Road, Newlyn
Roads are selected for re-sheeting based on a combination of factors, including road condition, traffic volumes, road hierarchy, feedback from Council’s road maintenance teams and reports received from the community. Council’s annual gravel re-sheet program is an important part of maintaining our extensive gravel road network, with this year’s investment in improved materials aimed at delivering longer-lasting roads and better outcomes for our communities.
What can motorists expect?
During the program, motorists may experience temporary traffic delays, reduced speed limits and increased truck and machinery movements. We ask motorists to take care when travelling through work areas, follow traffic management directions and be mindful of Council crews working on the roads.